General Information
Provider
Equinix
Colo Space
30,160 SF
Airport
N/A
Year Built
2000
Security
On-site
Uptime
N/A
Hyperscale
Enabled
Retail
Available
Wholesale
Available
Interconnectivity
Available
Overview
This Equinix facility is positioned at 9706 E Easter Avenue, Ste 160 in Englewood. The data center is a 30,160 SF purpose built facility. Infrastructure in the data center includes N+1 UPS and N+1 generator redundancies, with a cooling configuration of N+1.
Certifications
SSAE 16
PCI DSS
ISO
FISMA
NIST
SOC 1
SOC 2
Power & Infrastructure
Utility Feeders
Dual Feed
UPS
Four (4) 225 kVA UPS systems; parallel redundant UPS configuration (N+1)
Standby Power
N+1
Cooling
N+1
Other Information
Network Providers
Level 3 (Lumen Technologies), AT&T, CenturyLink (Lumen), Zayo, Comcast, Verizon, Verizon Xo