General Information
Provider
Evoque Data Centers
Colo Space
194,057 SF
Airport
N/A
Year Built
1972
Security
On-site
Uptime
N/A
Hyperscale
Not Enabled
Retail
Available
Wholesale
Available
Interconnectivity
Available
Overview
Evoque Data Centers's CHI1 facility is located at 4513 Western Avenue in the Chicago market. The data center is a 194,057 SF retrofit facility. Connectivity to Megaport is available for customer use. The facility offers 2N UPS and N+1 generator redundancies.
Certifications
Power & Infrastructure
Utility Feeders
Dual Feed
UPS
Eight (8) UPS systems, each with two - four supporting 750kVA modules; power supplied to the eight UPS systems through diverse/redundant commercial power feeders and nine standby generators; UPS system designed to support full load for 15 minutes via internal battery plant (2N)
Standby Power
N+1
Cooling
N+1
Other Information
Network Providers
Zayo, Cogent Communications, CenturyLink (Lumen), AT&T, Comcast, Verizon, Lightower, Megaport, Hudson Fiber, Cloudflare, Extenet Systems, MCImetro Access Transmission Services, Everstream, SCC Data Systems