General Information
Provider
DataBank
Colo Space
193,000 SF
Airport
N/A
Year Built
1910
Security
On-site
Uptime
N/A
Hyperscale
Enabled
Retail
Available
Wholesale
Available
Interconnectivity
Available
Overview
DataBank's CLE1 facility is located in Cleveland. The 193,000 SF retrofit facility is designed to meet customer colocation needs. Carrier options at the data center include Level 3 (Lumen Technologies), Cogeco Cable and Verizon Telecom. UPS systems are configured in N+1 redundancy with N generators and N+1 cooling.
Certifications
Power & Infrastructure
UPS
Four (4), 203 kW UPS systems (N+1)
Standby Power
N
Cooling
N+1
Other Information
Network Providers
Level 3 (Lumen Technologies), Zayo, Cogent Communications, CenturyLink (Lumen), AT&T, XO Communications, Windstream Communications, Crown Castle, Verizon, Windstream Wholesale, Windstream, Verizon Xo, Time Warner Telecom, Sprint, Telia Sonera, Time Warner Cable, Gtt, Telia Carrier, TELUS Communications, Everstream, Rogers Communications, Fibertech Networks, Fusion, Verizon Telecom, Cogeco Cable, MTS Allstream, Cavalier, 360 Networks, Shaw Business, Hydro One Telecom, Bell Nexxia, Group Telecom, Sprint Canada